sample="quota" bates="2058105033" isource="pm" decade="1990" class="ni" date="19930118" Jewett Automation COPY Engineering and Design Services Robotic and Automation Systems To: Wes Sanderson, Philip Morris, Inc. Bill Keen, Philip Morris Lane Kelly, Jewett Automation Rob Scott, Jewett Automation Richard Reich, Jewett Automation Edwin Cutright, Jewett Automation David Brown, Dallas Electrical From: Eric A. Lewis Date: January 18, 1993 Subject: Progress report/Expense update, Autosplice System Machine assembly is complete. Initial manual tests of the web knife and the splicing cylinder have been performed and at this point are operating properly. The electrical wiring has slipped until January 18. It is anticipated that the wiring effort will take two days. After completion of the wiring the machine will be sent to the Jewett Annex to begin the debug process. Due to end of year accounting Jewett Automation costs are current up to Jan. 10, Dallas Electrical costs are current up to Jan. 17. Costs to Date: Engineering...$20,305.50 Fabrication...$11,699.57 Purchased Items...$18,023.21 Dallas Electrical...$7,912.59 Total...$57,940.87 Regards, Eric A. Lewis Project Engineer 2901 Maury Street Richmond, VA 23224 (804) 233-9861 FAX (804) 233-6732